基于案例的我国PPP项目再谈判情况研究
刘婷 赵桐 王守清
(1.清华大学建设管理系,北京 100084;2.清华大学恒隆房地产研究中心,北京 100084)
文献要素
摘要:通过文献调研对我国二十世纪九十年代以来的38个发生重大再谈判的PPP项目进行案例分析,梳理引起再谈判的原因和结果。研究发现,引起再谈判的主要原因包括市场需求风险、政府信用问题及政策法律变更等,再谈判导致的主要结果是社会资本退出或调整投资回报机制。针对暴露出的问题,从项目前期研究、弹性条款与再谈判机制、政府信用、政府责任等四个方面提出建议。
关键词:再谈判;PPP;案例分析;社会资本;政府信用
Abstract:This paper identifies 38 typical renegotiated PPP projects since 1990s in China based on literature review,and makes the case analysis. Then,analyzes and categorizes the causes and outcomes of these renegotiations. Research shows that revenue risk,government credit risk,law and policy change risk are dominant causes of renegotiations,and renegatiations generally end up with adjustment of contract terms regarding to revenue allocation,or contract termination with the exit of the private partner. Finally,proposes policy recommendations on project front-end analysis,flexible contract terms and renegotiation mechnism,government credit,and government accountability. 
Keywords:renegotiation;public private partnership;case analysis;private capital;government credit
参考文献
[1] 亓霞,柯永建,王守清.基于案例的中国PPP项目的主要风险因素分析[J].中国软科学,2009(5):107-113.
[2] World Bank Group. Private participation in infrastructure database[EB/OL].(2015-12-15)http://ppi.worldbank.org/customquery.
[3] 孙慧,孙晓鹏,范志清.PPP项目中再谈判关键影响因素的研究[J].国际经济合作,2010(3):58-61.
[4] Xiong W,Zhang X. The real option value of renegotiation in Public-Private Partnerships[J]. Journal of Construction Engineering & Management,2016(2).
[5] Engel E,Fischer R,Galetovic A. Soft budgets and renegotiations in Public-Private Partnerships[R].National Bureau of Economic Research,2009.
[6] 柯永建.中国PPP项目风险公平分担[D].北京:清华大学,2010.
[7] 刘婷,王守清,盛和太,等.PPP项目资本结构选择的国际经验研究[J].建筑经济,2014(11):11-14.
[8] 赵国富,王守清.基础设施BOT/PPP项目中的政府责任研
究[J].商场现代化,2007(14):194-195.
[9] 王守清,刘婷.PPP项目监管:国内外经验和政策建议[J].地方财政研究,2014(9):7-12.
建筑经济,2016(09):31-34
下载地址

    你还没注册?或者没有登录?这篇论文要求至少是本站的注册会员才能阅读!

    如果你还没注册,请赶紧点此注册吧!

    如果你已经注册但还没登录,请赶紧点此登录吧!