关键链和滚动计划思想在高铁施工进度计划中的应用初探
黄明真
(同济大学, 上海 201804)
文献要素
[摘 要] 改进了关键链和滚动计划思想,将其应用于我国高速铁路施工进度计划中。具体步骤为:构建年、季度、月三级进度计划;采用改进的关键链思想制定可操作的月进度;在年和季度进度的动态管理上,采用改进的滚动计划思想,随施工阶段的不同而变化滚动长度,防止计划工作量的大幅加大。
[关键词] 高速铁路;关键链;滚动计划;进度计划
Abstract: After making some improvement on critical chain and rolling planning concepts, this paper adopted them into the process of construction scheduling for high-speed railway projects. The concrete steps of scheduling were as follows. First, establish a three-hierarchy structure of schedule plans. The intervals of the three hierarchies are year, quarter and month. Second, make the operational month schedule with the improved critical chain. Third, carry out the dynamic management of the quarter and year schedules using the improved rolling planning.
Key words:  high-speed railway; critical chain; rolling planning; construction schedule planning
[参考文献]
[1]宋剑.京津城际轨道交通工程建设管理实践[J].建筑经济,2008,310(8):14-16.
[2]魏红武.对滚动计划法中几个理论问题的初探[J].华东经济管理,1988,5(1):73-74.
[3]赵之友.关键链项目管理评价[J].科技管理研究,2008(7):496-499.
[4]Jerzy Stawicki.组织中的项目——基于约束理论和关键链理论的管理方法[J].项目管理技术,2008(1):68-72.
[5]吉罗德·肯德尔. 关键链项目管理[J]. Enterprise Management,2007(5):62-67.
[6]Eliyahu M. Goldratt&Jeff Cox. The goal: a process of ongoing improvement (2nd ED) [M].上海:上海三联书店,1999.
[7]Tzvi Raz,Robert Barnes,Dov Dvir. A critical look at critical chain project management[J].Project Management Journal,2003,34(4):24-32.
[8]寿涌毅.关键链项目管理方法综述[J].项目管理技术,2006(9):28-31. 
建筑经济,2009(7):23-26

 

下载地址

    你还没注册?或者没有登录?这篇论文要求至少是本站的注册会员才能阅读!

    如果你还没注册,请赶紧点此注册吧!

    如果你已经注册但还没登录,请赶紧点此登录吧!