国际工程成本风险分析与对策
李锐娟 王玉平 陈晖
(1.中国航空规划设计研究总院有限公司,北京 100120;2.林产工业规划设计院,北京 100010)
文献要素
摘要:针对因国际工程前期准备投入大、中标率低致使我国建筑企业难以承受而面临巨大成本风险的问题,分析导致国际工程价格风险、延期赔偿风险以及成本增加风险等成本风险的原因,提出与当地公司组建联合体投标,在合同签订前进行造价重测、工期重测以及细化合同等应对策略,为我国企业降低国际工程成本风险提供参考。
关键词:建筑企业;国际工程;成本风险;对策
Abstract:Considering the problem of tremendous cost risk in international engineering faced by Chinese construction enterprises as a result of large investment in bid preparation and low bidding rate,the paper analyzes the reasons for price risk,delay compensation risk and cost increasing risk in international engineering,provides countermeasures from the prospective of joint bid with local companies,recalculate engineering cost before contract signing,recalculate schedule of project and deepen contract,providing reference for Chinese enterprises to reduce the cost risk of international engineering.
Keywords:construction enterprise;international engineering;cost risk;countermeasure
参考文献
[1] 赖振玮.浅析国际工程总承包方面临的主要风险与对策[J].工程经济,2014(11):27-32.
[2] 倪伟峰,谷永强,姚伟涛.怎样搞砸海外项目[J].新世纪,2011(29).
[3] 齐荣光,梁权.从中铁建沙特巨亏看海外工程项目风险管
理[J].会计之友,2011(7上):20-21.
[4] 徐树人.某国际承包工程风险管理分析[J].中国招标,2012(21):37-39.
[5] 黎晓婷.浅谈国际工程投标报价的方法和技巧[J].中国水运,2013(13):227-229.
[6] 杜军良,陈政.浅析目标成本管理在公路工程施工项目中的应用[J].工程经济,2015(3):24-28.
[7] 曹静.如何做好国际工程投标报价[J].内蒙古石油化工,2009(1):63-64.
[8] 屈锦红.国际建筑工程风险源与防范策略[J].建筑,2012(11):80-81.
[9] 薛玉华.关于如何规避国外工程风险的若干思考[J].现代经济信息,2013(6):184,191.
[10] 魏飞,陈军杰.EPC模式下承包商的工期风险防范[J].工程经济,2013(4):3-4.
[11] 李清桥,陈林.国际工程项目策划阶段风险管理[J].四川水利,2013(1):59-62.
建筑经济,2016(03):16-19
下载地址