不利物质条件下建设项目合同补偿研究
严玲 丁乾星 张笑文
(天津理工大学管理学院,天津 300384)
文献要素
摘要:建设项目施工过程中不利物质条件引发的补偿问题是发承包双方容易产生争议的焦点。本文以合同补偿的责任判定、补偿原则和补偿路径为主线,通过多个索赔案例分析不利物质条件引起的补偿责任判定的依据,在此基础上探索与之相适应的合同补偿原则与补偿路径:基于合同自我履行原则的工程变更、基于再谈判原则的索赔和基于第三方治理原则的情势变更。
关键词:不利物质条件;风险责任;补偿路径;合同补偿
Abstract:The compensation caused by adverse material conditions is the disputed point between the employer and contractor in construction project. This paper follows the main logic to research as risk responsibility,compensate principle and compensate paths. Through the analysis between several claim cases,summarizes the gist for predicting risks responsibility,and after to explore and explain three corresponding compensate principle and paths:variation order under self-performing principle,claim under renegotiation principle,changed situation under the third party governance.
Keywords:adverse material conditions;risk responsibility;compensate paths;contract compensation
参考文献
[1] 翟冬.论“有经验的承包商”[J].法治与社会,2014(10):102-103.
[2] 张之梁.不可预见地质条件索赔问题探讨[J],山西水利科技,2013(3):94-96.
[3] Yaw Frimpong,Jacob Oluwoye,Lynn Crawford. Causes of delay and cost overruns in construction of groundwater projects in a developing countries:Ghana as a case study[J].International Journal of Project Management,2003(21):321-326.
[4] 郭章林,孙雨丽.基于FIDIC准则的自然灾害合同条件研
究[J].建筑经济,2009(12):23-25.
[5] 严敏,闫金芹,严玲.清单计价模式下施工合同风险再分担路径研究[J].建筑经济,2014(10):90-94.
[6] 杨鹂鸣,罗汀.工程变更与施工索赔问题的探讨[J].基建优化,2005,26(5):25-28.
[7] 石心刚.合同签约与履约两阶段中的风险分担框架构建分析[J].建筑经济,2014(12):94-96.
[8] 白洁,贺星红,姜玉林.工程合同不完备性补偿机制的构建研究[J].工程经济,2015(2):40-44.
[9] 刘庭.工程项目管理过程中施工索赔的起因与索赔技巧[J].科学之友,2010(3):85-87.
[10] 孙九玉.变更索赔的着力点[J].施工企业管理,2014(10):31-32.
[11] 顾东林.运用情势变更原则解决建材价格异常波动争议[J].建筑经济,2009(8):59-61.
建筑经济,2015(11):55-59
下载地址

    你还没注册?或者没有登录?这篇论文要求至少是本站的注册会员才能阅读!

    如果你还没注册,请赶紧点此注册吧!

    如果你已经注册但还没登录,请赶紧点此登录吧!