基于进度的工程价款管理研究
孙凌志 杭晓亚
(山东科技大学土木工程与建筑学院,山东 青岛 266590)
文献要素
摘要:在紧密结合行业标准、规范,深入研究进度对工程价款影响机理的基础上,通过分析施工组织设计与合同文件之间的关系,进一步明确作为工程价款管理依据的进度;针对性的提出基于进度的工程价款管理措施。期望对规范各方主体计价行为,推进全要素造价管理,认定完善市场决定工程造价机制起到重要参考意义。
关键词:工程进度;工程价款;影响机理;价款管理
Abstract:Combined with the industry standard and specification closely and thorough research of the scheduling influence on construction price,further defines the source of scheduling which is the basis of the management of construction price through the analysis of the relationship between the construction organization design and contract documents. Then puts forward some targeted measures for the management of construction price based on scheduling. This paper has great significance for regulating all the parties’ valuation behavior,promoting the management of total factor cost and improving the mechanism of construction price decided by the market.
Keywords:construction scheduling;construction price;influence mechanism;price management
参考文献
[1] 张树捷.BIM在工程造价管理中的应用研究[J].建筑经济,2012(2):20-24.
[2] 上海市全国人大代表.上海“建设工程质量安全”调研报告[EB/OL].(2011-10-25)http://www.cpmchina.com.
[3] 何伯森.工程项目管理的国际惯例[M].北京:中国建筑工业出版社,2007.
[4] 住房和城乡建设部.建设工程工程量清单计价规范[S].北京:中国计划出版社,2013.
[5] 贾宏俊.建设工程技术与计量[M].北京:中国计划出版社,2009.
[6] 于斌.施工组织设计的法律地位[J].施工技术,2014(6):504-509.
[7] 田可耕,朱静.让施工组织设计不再被束之高阁[J].施工企业管理,2013(4):20-24.
[8] 纪凡荣,曲娣,尚方剑.BIM情景下的可视化工程进度管理研究[J].建筑经济,2014(10):40-43.
建筑经济,2015(03):65-69
下载地址

    你还没注册?或者没有登录?这篇论文要求至少是本站的注册会员才能阅读!

    如果你还没注册,请赶紧点此注册吧!

    如果你已经注册但还没登录,请赶紧点此登录吧!