2013版清单计价规范下甲供材料结算探讨
徐南
(1.江苏建筑学院建筑工程管理学院,江苏 徐州 221116;2.徐州方圆工程建设监理公司,江苏 徐州 221116)
文献要素
摘要:《建设工程工程量清单计价规范》(GB50500-2013)对“发包人提供材料和工程设备”作出规定,但是在实际执行过程中容易发生理解偏差,造成甲供材料结算错误。为规避此问题,本文通过对甲供材供货方式及甲乙双方应承担的责任以及风险进行分析,讨论甲供材供货方式下甲供材料的计算方法,并提出做好结算的三点建议。
关键词:甲供材料;计价规范;结算方法;扣回单价
Abstract:The provisions of “the material and engineering equipment provided by the employer” under “Code of valuation with bill quantity of construction works ”(GB50500-2013),causes understanding deviation easily in the actual execution process,results in the material which is provided by the employer settlement mistake. To avoid this problem,analyzes the material which is provided by the employer delivery mode and both parties undertake responsibility and risk,discusses the calculation method of the materials which is provided by the employer back price. Lastly,puts forward three suggestion for improving settlement.
Keywords:material provided by the employer;valuation standard;settlement method;back price
参考文献
[1] 住房和城乡建设部.建设工程工程量清单计价规范GB50500-
2013[S].北京:中国建筑工业出版社,2013.
[2] 全国造价工程师执业资格考试培训教材编审委员会.建设工程计价[M].北京:中国计划出版社,2013.
[3] 刘钟莹.建设工程工程量清单计价[M].南京:东南大学出版社,2010.
[4] 王艳艳,任宏,等.定额与清单计价模式下甲供材料结算与退还研究[J].建筑经济,2014(7).
建筑经济,2015(01):59-61
下载地址

    你还没注册?或者没有登录?这篇论文要求至少是本站的注册会员才能阅读!

    如果你还没注册,请赶紧点此注册吧!

    如果你已经注册但还没登录,请赶紧点此登录吧!