设计-建造总承包管理的国际研究进展(二)—基于研究主题的文献综述
张尚 任宏 Albert P.C. Chan3
(1.苏州科技学院,江苏 苏州 215011;2.重庆大学,重庆 400045;3.香港理工大学,香港)
文献要素
摘要:基于648篇关于DB总承包管理英文文献的统计分析,表明DB与其他模式绩效的比较、DB模式的合同问题、DB承包商的选择等,是重要的研究主题。本文采用文献综述的方法探讨这些研究主题的重要成果,主要研究结论包括:DB模式具有节约工期、降低成本的显著优势;DB项目应采用两阶段、最优价值的承包商选择方法;DB模式在应用过程中最大的阻力来自业主和法律;DB项目设计管理中最重要的是合理确定业主与承包商完成的设计比例;DB承包商、业主、项目团队、招标文件是最重要的DB项目成功要素。在此基础上,提出了国内DB模式的研究方向。
关键词:行业管理;设计-建造模式;总承包管理;研究进展;文献综述
Abstract:Based on the statistic analysis of 648 pieces of English literature on DB general contracting management,finds that DB performance comparison with other models,DB contract,DB contractor selection,etc.,are important research topics. This paper mainly explores the research conclusions for each topic through literature review method. The research findings are:DB has advantages of time saving and cost reducing;DB project should use two-stage best-value contractor selection method;most of the barriers in applying DB come from client and law;the most important issue in DB design management is to decide the proper ratio of design between client and contractor;DB contractor,client,project team,and tendering documents are critical success factors of DB project. Based on the above findings,proposes future research directions for researcher of DB model to carry out relevant research in China.
Keywords:industry management;design-build model;general contracting management;research progress;literature review
参考文献
[1] M. Konchar. A comparison of United States project delivery systems[R]. Technical Report No.38,Computer Integrated Construction Research Program,Pennsylvania State University,US,1997.
[2] D. Gransberg. Design/Build in transportation:From the research perspective[J]. Leadership and Management in Engineering,2003,3(3):133-141.
[3] A. M. A. Aziz. A survey of the payment mechanisms for transportation DBFO projects in British Columbia[J]. Construction Management and Economics,2007(25):529-543. 
[4] R.A. Perkins. Sources of changes in design-build contracts for a governmental owner[J]. Journal of Construction Engineering and Management,2009,135(7):588-593. 
[5] T.C. Becker,J.S. Shane,E.J. Jalselskis. Comparative analysis of lean construction with design-build using a framework of contractual forms of agreement[J]. Journal of Architectural Engineering,2012,18(2):187-191.
[6] J. Oliveira. Design-Build method viewed by public agencies in Southern Nevada compared to Arizona and Utah[D]. Las Vegas:University of Nevada,2003. 
[7] J. Bourne,S. DeWitt,P. Drennon. Ensuring quality is built into the request for proposal process[R]. Transportation Research Board,National Research Council,Washington,D.C.,2006.
[8] K.R. Molenaar,A.D. Songer. Model for public sector design-build project selection[J]. Journal of Construction Engineering and Management,1998,124(6):467-479.
[9] K.J. Potter,V. Sanvido. Implementing a design build prequalification system[J]. Journal of Management in Engineering,1995,11(3):30-34.
[10] B. Xia,A. Chan,J. Zuo,K. Molenaar. Analysis of selection criteria for design-builders through the analysis of requests for proposal[J]. Journal of Management in Engineering,2013,29(1):19-24.
[11] G.S. Harris. The significance and promotion of good design in design and construct civil engineering projects[C]. Seminar Proceedings on Design and Build Procurement System,Hong Kong,1999,61-65.
[12] J.J. Pfeifer. Selection criteria utilized by large private sector commercial owners in design-build method selection[D]. US:Michigan State University,2002.
[13] Q.G. William. Design Build for the Design Professional[M]. New York:Aspen Law & Business,2001.
[14] M.E Asmar,W. Lotfallah,G. Whited,A.S. Hanna. Quantitative methods for design-build team selection[J]. Journal of Construction Engineering and Management,2010,136(8):904-912.
[15] C.J. Anumba,N.F.O. Evbuomwan. Concurrent engineering in design-build projects[J]. Construction Management and Economics,1997(15):271-281.
[16] F. Pena-Mora,M. Li. Dynamic planning and control methodology for design build fast-track construction projects[J]. Journal of Construction Engineering and Management,2001,127(1):1-17.
[17] K. Cho,C.T. Hyun,K. Koo,T. Hong. Partnering process model for public-sector fast-track design-build projects in Korea[J]. Journal of Management in Engineering,2010,26(1):19-29.
[18] F.Y.Y. Ling,B.H.M. Poh. Problems encountered by owners of design-build projects in Singapore[J]. International Journal of Project Management,2008(26):164-173.
[19] D.O. Cox. Contract administration:technology and practice in Europe[R]. Report FHWA-PL-02-0xx,Federal Highway Administration,Washington,D.C.,2002.
[20] American Association of State Highway and Transportation Officials(AASHTO). Design-build environmental process and level of detail:eight case studies[R]. Washington D.C.,2005.
[21] Federal Construction Council(FCC). Experiences of federal agencies with the design-build approach to construction[R]. National Academy Press,Washington,D.C.,1993.
[22] Federal Highway Administration(FHWA). Design-build effectiveness study:final report[R]. Washington,D.C.,2006.
[23] V. Sanvido,F. Grobler,K. Parfitt,M. Guvenis,M. Coyle. Critical success factors for construction projects[J]. Journal of Construction Engineering and Management,1992,118(1):94-111.
[24] J.L. Beard,M.C. Loulakis,E.C. Wundran. Design-build:planning through development[M]. New York:McGraw-Hill,2001.
[25] F.Y.Y. Ling,S.L. Chan,E. Chong,L.P. Ee. Predicting performance of design-build and design-bid-build projects[J]. Journal of Construction Engineering and Management,2004,130(1):75-83.
建筑经济,2014(11):5-10
下载地址

    你还没注册?或者没有登录?这篇论文要求至少是本站的注册会员才能阅读!

    如果你还没注册,请赶紧点此注册吧!

    如果你已经注册但还没登录,请赶紧点此登录吧!