核电常规岛与火电项目施工管理成本差异分析
杨明生 付俊贵 薛俊龙
(中广核工程有限公司,广东 深圳 518124)
文献要素
摘要:核电常规岛工作原理与火电项目类似,但两者设计情况和质量管理、安全管理、建设工期等方面的差异,导致核电常规岛项目施工管理成本远高于火电项目。对核电常规岛项目与火电项目在设计和质量、安全、工期等方面的差异引起核电常规岛施工较高的管理投入进行分析,发现管理费和安全措施费用增加比例最高,以供同业参考。
关键词:核电常规岛;施工管理成本;差异分析
Abstract:The conventional island of nuclear power and thermal power project principle is similar,but the difference of design,quality management,safety management,construction period and other aspects,causes the conventional island of nuclear power project construction management input far higher than that of thermal power project. This paper analyses the difference of conventional island nuclear power project and thermal power project in the design,quality,safety,construction period and other aspects that cause higher management input in conventional island of nuclear power construction,finds that the increase proportion of management fees and safety measures fees is highest,for the colleague reference.
Keywords:conventional island of nuclear power;construction management cost;difference analysis
参考文献
[1] 桂小琴.核电站建造现场签证及零星委托管理方式探讨[J].建筑经济,2012(3).
[2] 孙莉.施工企业工程成本控制关键风险因子识别[J].施工技术,2014,43(15):98-101.
建筑经济,2014(10):83-85
下载地址

    你还没注册?或者没有登录?这篇论文要求至少是本站的注册会员才能阅读!

    如果你还没注册,请赶紧点此注册吧!

    如果你已经注册但还没登录,请赶紧点此登录吧!