考虑工期-投资相关性的BOT项目特许期决策研究
简迎辉 梅明月 鲍莉荣
(1.河海大学商学院, 江苏 南京 210098; 2.河海大学文天学院, 江苏 南京 243013)
文献要素
[摘 要] 针对BOT项目建设投资与工期的相关性,引入乔列斯基因子分解法,对原本相互独立的随机变量进行相关关系转换。基于项目投资者的角度,利用Monte Carlo模拟,建立工期-投资相关的BOT项目特许期决策模型,通过对工期、投资和特许期内NPV的模拟,确定较为合理的特许期区间。案例分析表明,该决策工具能够为BOT项目特许期的决策提供合理依据。
[关键词] BOT项目;特许期;工期-投资相关;Monte Carlo模拟
Abstract: For the correlation of BOT project investment and construction period, the method of Cholesky decomposition has been used to convert independent stochastic variables into correlative ones. The Monte Carlo simulation method can be used to model the decision-making of concession period for a BOT projects with correlation of time and investment. Thus a rational range of concession period can be obtained through simulations of construction period, investment and the NPV within concession period. The case study shows that this decision-making tool can provide a reasonable support for decision-making of BOT projects.
Key words: BOT project; concession period; correlation of time and investment; Monte Carlo simulation
[参考文献]
[1]Zhang XQ,Abourizk SM.Determining a reasonable conces-sion period for private sector provision of public works and services[J]. Canadian Journal of Civil Engineering,2006(5).
[2]赵振华.高速公路BOT项目特许期决策研究[D].山东:山东大学,2011.
[3]简迎辉,邱秋露,鲍莉荣.外生不确定条件下水利BOT项目特许期决策研究[J].中国农村水利水电,2013(9).
[4]刘永胜.基于实物期权的污水处理PPP项目特许期决策研究[D].成都:西南交通大学,2012.
[5]杨宝森,刘鲁,马晨.时间-费用相关的随机活动网络仿真研究[J].系统仿真学报,2010(4).
[6]杨宝森,刘鲁,马晨.基于仿真的随机活动网络进度费用联合风险[J].系统工程理论与实践,2010(11).
[7]王东波.不确定条件下BOT项目特许期决策模型研究[D].大连:大连理工大学,2010.
[8]Ke H,Liu B. Project scheduling problem with stochastic activity duration times[J]. Applied Mathematics and Comp-utation(S0096-3003),2005(1).
[9]李志伟.相关随机变量的蒙特卡罗模拟[J].统计与决策,2007(5).
[10]韩首栋.污水处理BOT项目特许期决策方法研究[D].大连:大连理工大学,2008.
[11]曹雷,顾祥柏,等.蒙特卡洛模拟风险分析中概率分布函数的选择[J].石油化工设计,2007(3).
建筑经济,2014(3):44-47