城市轨道交通BT项目的价款支付安排研究
(1.东南大学土木工程学院建设与房地产系, 江苏 南京 210096;2.昆山市淀山湖防洪工程管理处, 江苏 昆山 215300)
- 文献要素
-
[摘 要] 以适用于轨道交通BT项目的合同形式为基础,针对BT合同价款构成及支付安排,探讨支付方式、投融资费率及外界资源约束对支付安排的影响。通过算例对不同的支付安排进行比选,结合工程实际提出合理化建议,为城市轨道交通回购契约中的支付条款设计提供理论支持。[关键词] BT模式;支付方式;回购期限;投融资费率;资源约束Abstract: This paper is based on analysis of contract forms suitable for rail transit BT project, focused on the BT contract price and payment arrangement, and payment schedules influenced by payment patterns, investment and financing rate and external resource constraints are deeply discussed. Through example analysis, a comparison of different payment arrangements has been made. Some reasonable proposals of payment schedule are given in this paper, providing theoretical support for payment terms in repurchase contract of urban rail transit in our country.Key words: BT mode; payment pattern; repurchase term; investment and financing rate; resource constraint[参考文献][1]刘应宗,周晓丽.运用BT模式进行城市轨道交通建设[J].重庆交通大学学报:社会科学版,2007(3):15-18.[2]钟炜,王博.BT项目回购阶段业主方回购价款确定分析[J].建筑经济,2010(9):55-59.[3]严玲,杨艳荣.政府投资项目BT模式中回购基价的控制机制研究[J].建筑经济,2011(2):33-36.[4]匡亚萍.建筑项目支付进度安排问题研究[M].杭州:浙江大学出版社,2009.[5]王将军.市政基础设施BT项目的回购期及回购担保[J].建筑经济,2012(1):56-58.建筑经济,2014(3):40-43