建设项目工程延期的影响因素研究—基于重庆的实证分析
曹小琳 彭玉石
(重庆大学建设管理与房地产学院, 重庆 400045)
文献要素
[摘 要] 建设工程项目工程延期的影响因素错综复杂。综合运用文献研究、现场访谈、问卷调查和主成分分析方法,对重庆市建设工程项目工程延期问题进行实证分析。分析结果表明,工程款支付不及时、建设前期决策缓慢、各设计专业协调不力是影响工程延期最主要的三个因素,并采用SPSS软件对39个工程延期影响因素进行主成分分析,得到重新命名的主成分因子,分别为:施工现场管理因子、设计管理因子、资金流管理因子、项目沟通管理因子、项目前期准备因子,进而针对每个因子提出防范工程延期的对策建议。
[关键词] 工程延期;影响因素;主成分分析
Abstract: The influencing factors of the source of construction project duration extension are complicated. Made comprehensive use of literature research, on-site interviews, surveys, and principal component analysis, the empirical analysis of the research is taken in Chongqing. It's found that project payment not timely, pre-construction decisions too slow, Weaknesses in the coordination of design professionals are the three main factors affecting the construction delay. As for the 39 factors, with the SPSS software for principal component analysis, renaming the principal component factors were construction site management factor, design factor, capital flow management factor, project communication management factor, project preparatory factor, and specific recommendations are given for each factor.
Key words: construction delays; influencing factors; principal component analysis
[参考文献]
[1]Ogunlana S.O., Promkuntong, Kand Vithool. Construction delays in a fast-growing economy: comparingThailand with other economies[J]. International Journal ofProject Management.1996,14(1):37-45.
[2]FrimpongY., Oluwoye. Significant factorscausing delay and cost overruns in construction of groundwaterprojects in Ghana[J]. Journal of Construction Research.2003,4(2):175-187.
[3]http://en.wikipedia.org/wiki/Likert_scale[EB/OL].
[4]曾五一,肖红叶.统计学导论[M].北京:科学出版社,2007.
[5]Moser, C. A., Kalton.Survey methods in socialinvestigation [G].Heinemann Educational,London,1971.
[6]MuraliSambasivan, Yau Wen Soon, Causes and effects of delays in Malaysian construction industry[J]. International Journal of Project Management 2007,25:517-526.
[7]任宏,张巍.工程项目管理[M].北京:高等教育出版社,2005.
建筑经济,2013(12):36-40