- 文献要素
-
[摘 要] 传统挣值法主要适用于工程量清单合同条件下施工单位项目管理活动。以传统挣值法为基础,以解决挣值法的基本方法与EPC总包项目的适应性和实现其在EPC总包项目中正确应用为目的,改进挣值(EV)的计算方法,引入新参数“产出计划值(OPV)”,以解决挣值法与EPC总包项目的适应性问题,并将成本偏差分解为由于工程量变化引起的成本偏差CV(Q)和由于价格变化引起的成本偏差CV(P),便于准确揭示成本变化的具体原因,进而采取针对性的偏差控制措施。对同一案例分别用传统方法和改进后的方法进行分析,结果表明改进后的指标体系能更准确的反映EPC总包项目成本、进度状态和控制效果。
[关键词] 挣值法;参数;悖论;EPC项目;解决方案
Abstract: The traditional Earned Value Method(EVM) is mostly used at the condition of BOQ. Based on traditional EVM, to resolve the compatible between the traditional EVM and the EPC project, and realize the actual use in the EPC project. The calculation method of EVM is improved through introducing the new parameter OPV(Output Planned Value), resolved the compatibility between the traditional EVM and the EPC project, and separate the Cost Variance(CV) into two aspects: the CV caused by the Quantities(CV(Q)) and the CV caused by the Price (CV(P)),so we can analysis the specific reasons of the CV, and then take targeted deviation control measures. Contrast with traditional method, the results show that the improved index system is more accurately reflect the EPC project cost, schedule status and control effect.
Key words: EVM; parameter; conflicting; EPC project; solution
[参考文献]
[1]陈威.基于EVM的火电工程投资管理信息系统的研究[D].保定:华北电力大学.2009.
[2]张轶斐,陈铭.发电总承包项目赢得值实现方法研究[J].电力勘测设计.2010(1).
[3]俞启元,吕玉惠,张尚.施工项目进度成本集成计划和控制方法研究[J].建筑经济,2012(7).
[4]李焱,刘士李.赢得值法在电网工程项目施工管理中的应用[J].华东电力.2012(7).
[5]赵万林.水电工程项目管理及赢得值管理应用[D].天津:天津大学.2009.
[6]王德敏,吴遥.浅谈EPC项目管理模式对输电线路工程中造价的影响[J].建筑经济,2012(7).
[7]陈铭.电力EPC项目的造价管理问题探讨.建筑经济[J].2010(8).
[8]全国一级建造师执业资格考试用书(第三版)[M].北京:中国建筑工业出版社,2011.
建筑经济,2013(10):40-42