市政基础设施BT项目的回购期及回购担保
(上海中鑫建设咨询有限公司, 上海 200023)
- 文献要素
-
[摘 要] 结合《中国人民银行贷款通则》以及其他商业银行的贷款规定,对BT项目回购期提出建议,即回购期一般不应短于项目的缺陷责任期,且回购期与建设期合计不应超过10年。就回购期及支付方式对回购款的影响进行比较;并就回购担保重点阐述现行BT项目回购担保的类型以及选择原则。[关键词] 基础设施,BT,回购期,回购担保,项目融资Abstract: In combination with the“People's Bank of China, Lending General Provisions” and loan provisions of other commercial banks, this paper gives some suggestions about the buy-back period of BT project, i.e. buy-back period should not be shorter than the defects liability period, and adds up the buy-back period and the total construction period less than 10 years. There are many different effects of different buy-back period and different payment terms on buy-back, the paper makes a comparison of these effects, then introduces the type and the select principles of buy-back guarantees.Key words: infrastructure; BT; buy-back period; buy-back guarantees; project financing[参考文献][1]王光荣.城市基础设施BOT/BT项目招商若干问题研 究[M].杭州:浙江大学出版社,2010.[2]博古今.新华词典[M].呼和浩特:内蒙古大学出版社,2009.[3]湖北省葛店开发区药谷国有资产有限公司.湖北省葛店经济技术开发区大湾社区工程建设项目BT融资招标公告(二次招标)[EB/OL].www.zhaobiao.gov.cn/z/notice/2010/3/30/24672052.shtml.2010-03-30.建筑经济,2012(1):54-56