您现在的位置:建筑经济>>往期回顾>2011年>第2期>>文献要素
新加坡与重庆预制混凝土业的JIT管理对比研究
郑应亨 任宏 吴旻
(1.重庆大学建设管理与房地产学院, 重庆 400030;2.重庆市巴南区建设委员会, 重庆 400055;3.重庆交通大学管理学院, 重庆 400074)
文献要素
[摘 要] 调查了重庆和新加坡预制混凝土业的JIT(及时)生产技术现状。通过对35家企业的实地考查发现:所有被调查厂家的预制混凝土都是按订单量生产。而原材料有的是采用经济订货量(EOQ)采购,有的是采用JIT(及时)采购。这个研究说明预制混凝土业原材料采购是可以采用JIT(及时)模式的。
[关键词] JIT采购,混凝土,调查,管理
Abstract: The paper surveys the implementation status of JIT in the ready mixed concrete(RMC) industry in Chongqing and Singapore. After survey of 35 RMC suppliers, it shows that all the RMC suppliers surveyed are using demand pull system to manage RMC production. However, the study also shows that the raw materials can be purchased either using the JIT purchasing method or the traditional economic order quantity(EOQ) purchasing method. The study shows that JIT can be used in the raw material procurement patterns of RMC.
Key words: JIT purchasing; concrete; survey; management
[参考文献]
[1]Andrew CG. Implementing JIT/TQC, readings in zero inventory[M].Falls Church, VA: APICS, 1984.
[2]Monden Y. Toyota production system-an integrated approach to Just-In-Time[M].3rd edition. Georgia:Engineering & Management Press,1998.
[3]Wang SQ, Ofori G, Teo CL. Productivity of ready mixed concrete in Singapore[J].Journal of Construction Research,2001,2:57-66.
[4]Norris DM. A study of JIT implementation techniques using the analytic hierarchy process model[J].Production and Inventory Management Journal,1992,12(1):49-53.
[5]Ramarapu NK, Mehra S, Frolick M. A comparative analysis and review of JIT “implementation” research[J].International Journal of Operations and Production Management,1994,15(1): 38-49.
[6]Williams JR, Tice HS. A program for communicating just-in-time concepts to smaller manufacturing vendors,Readings in Zero Inventory[M].Fall Church, VA: APICS,1984:170-193.
[7]Howser KJ Vendors. Proceedings of the APICS Annual International Conference[M]. Falls Church, VA: APICS,1984:378-379.
[8]Youngkin JM. Implementing zero inventory production in a job shop manufacturing environment, readings in zero inventory[M].Falls Church, VA: APICS,1984:63-66.
[9]Kolodiejski K. Zero inventory (just-in-time) education: integrating what already exists, readings in aero inven-
[10]Goddard WE.Just-in-time: surveying by breaking tradition[M].Essex Junction, VT: Oliver Wight Limited Publications, Inc,1986.
[11]Mehra S, Inman RA. Determining the critical elements of just-in-time implementation[J].Decision Science,1992,23(1):160-174.
[12]Zacharia G. Ready mixed concrete [M].Madras, 1985.
[13]城投预制混凝土厂.预制混凝土厂可行性研究报告[R].2003.
[14]李慧民,等.建设工程技术与计量[M].北京:中国计划出版社,2003:104-108.
[15]Schniederjans MJ, Cao Q.EOQ with a price discount: an expansion of inventory costs[J].International Journal of Production Economics,2000,65(3):289-294.
[16]Schniederjans MJ, Cao Q.An alternative analysis of inventory costs of JIT and EOQ purchasing[J].International Journal of Physical Distribution & Logistics Management,2001,31(2):109-123.
建筑经济,2011(2):87-92