110kV钢结构变电站机械化施工技术经济性研究
(深圳供电规划设计院有限公司,广东 深圳 518000)
- 文献要素
-
摘要:针对深圳地区110kV钢结构变电站机械化施工开展全面经济分析研究。研究选取深圳本地变电工程案例,采用典型案例分析法,引入全寿命周期成本(LCC)模型,综合考虑各项费用,定量评估不同施工方案对应的增量经济效益。分析结果表明,相较于传统施工模式,机械化施工在110kV钢结构变电站工程建设中具备较高的综合经济性,有助于提高工程质量和施工效率。关键词:110kV变电站;钢结构;机械化施工;经济分析;全寿命周期成本(LCC)Abstract:This paper conducts a comprehensive economic analysis of mechanized construction for 110kV steel structure substations in Shenzhen. Typical local substation engineering cases in Shenzhen are selected in the research. The typical case analysis method is adopted together with the life cycle cost(LCC)model. Taking various types of costs into consideration,the incremental economic benefits corresponding to different construction schemes are quantitatively evaluated. The analysis results show that compared with the traditional construction mode,mechanized construction presents favorable comprehensive economic performance in the construction of 110kV steel structure substation projects,and helps improve engineering quality and construction efficiency.Keywords:110kV substation;steel structure;mechanized construction;economic analysis;life cycle cost(LCC)参考文献[1] 缪叶,周鸿斌,颜立军.钢结构变电站与钢筋混凝土变电站全寿命周期成本分析[J].机电信息,2020(32):95-97.[2] 宋妙环,孙永彦,丁艳,等.基于结算监督视角的输变电工程结算关键风险点及控制措施研究[J].建筑经济,2026(2):51-57.[3] 冯希亚,李翠凤,陈茂迁,等.基于PSO-LSSVM-KDE模型的架空输电线路工程造价预测分析[J].建筑经济,2026(9):78-86.[4] 深圳市建筑产业化协会.“十三五”深圳市装配式建筑发展报告[J].建筑,2022(15):20-29.[5] 张飞强.装配式变电站探索与安装技术[D].杭州:浙江大学,2011.[6] 孙永彦,白永利,张晓梅,等.装配式变电站施工过程成本影响因素及控制措施[J].建筑经济,2020(12):58-63.建筑经济,2026(11):100-106