基于多案例分析的最高投标限价编制要点研究
(广西农业职业技术大学,广西 南宁 530007)
- 文献要素
-
摘要:最高投标限价是建设项目招投标阶段投资管控的法定上限,其编制质量直接决定招投标工作的质效。采用工程量清单计价模式的最高投标限价,工程量清单的准确性、完整性由建设单位负责,投标人依据建设单位提供的工程量清单自主报价。若清单出现漏项、项目特征描述不清或计量偏差等情况,将极易引发施工阶段工程变更与费用调整,进而造成项目投资增加。针对最高投标限价编制中的多个关键环节,结合典型案例进行剖析,提炼标准化编制流程与管控要点,旨在为其他建设项目投资管控提供可借鉴经验,保障建设资金规范高效使用。关键词:最高投标限价;投资管控;造价管理Abstract:The maximum bid price serves as the statutory upper limit for investment control during the bidding stage of construction projects. Its preparation quality directly determines the efficiency and effectiveness of the bidding process. Under the bill of quantities(BOQ)valuation model,the accuracy and completeness of the BOQ are the responsibility of the project owner,while bidders submit their quotes based on the BOQ provided by the owner. If the BOQ contains omissions,unclear item descriptions,or measurement deviations,it can easily lead to engineering changes and cost adjustments during the construction phase,thereby increasing project investment. This paper examines several key aspects of maximum bid price preparation,analyzes typical cases,and proposes standardized preparation procedures and controling key points. The aim is to provide experience reference for investment control in other construction projects and to ensure the standardized and efficient use of construction funds.Keywords:maximum bid price;investment control;cost management参考文献[1] 鲍婷婷.T区校园工程财政投资评审问题及对策研究[D].徐州:中国矿业大学,2022.[2] 屈雪林.财政投资预算评审中建安工程费评审的常见问题及对策研究[J].建筑经济,2024(6):38-40.[3] 黄海涛,黄文巧.关于政府部门审计结论作为工程造价结算依据的探究[J].工程造价管理,2024(4):32-37.[4] 孔军.财政投资评审质量控制现状及对策[J].财讯,2023(9):108-110.[5] 宋群荣,邝渝阳.工程项目造价管理的问题及控制策略探讨——基于高校基建管理部门的视角[J].高校后勤研究,2024(S1):181-182.[6] 王晶.工程变更对建筑工程造价影响的分析研究[J].城市建筑,2024(24):207-210.建筑经济,2026(8):84-90