EPC工程总承包项目实施阶段造价控制措施研究
(上海申元工程投资咨询有限公司,上海 200070)
- 文献要素
-
摘要:以某科技馆项目为例,从造价咨询人视角,阐述EPC工程总承包项目实施阶段造价控制的常见问题及相应控制措施,通过积极参与优化设计、制定谈价策略、严格审核施工措施方案、落实审批制度等途经,细化EPC工程总承包项目实施阶段造价控制手段。关键词:EPC工程总承包;施工图预算;造价控制措施Abstract:Takes a science and technology museum project as a case,from the perspective of a cost consulting professional,discusses common issues and corresponding control measures for cost management during the implementation phase of EPC engineering general contracting projects. By actively participating in design optimization,developing pricing strategies,strictly reviewing construction planning schemes,and enforcing approval procedures,elaborates on cost control methods in the implementation phase of EPC projects.Keywords:EPC engineering general contracting;construction drawing budget;cost control measures参考文献[1] 住房和城乡建设部,国家市场监督管理总局.房屋建筑和市政基础设施项目工程总承包管理办法[EB/OL].(2019-12-23). https://www.mohurd.gov.cn/gongkai/zc/wjk/art/2019/art_17339_243363.html.[2] 吴文毓.建筑项目EPC总承包模式下工程造价控制要点探析[J].中国住宅设施,2021(7):57-58.建筑经济,2026(7):37-41