建设项目施工阶段成本动态控制体系构建与应用研究
(蚌埠康恒建设工程有限公司,安徽 蚌埠 233000)
- 文献要素
-
摘要:为解决施工阶段成本控制中数据采集滞后、进度与成本信息割裂、材料浪费严重等突出问题,本研究构建了融合BIM+5D联动模型、改进挣值法(EVM)与四量分析可视化的成本动态控制体系。该体系通过构件级进度—成本实时关联、每小时自动计算的实时成本偏差(RCD)预警机制,以及主材预算量/采购量/消耗量/库存量的四量动态对比,实现了施工成本的动态监控与精细管控。实证应用表明,该体系为施工阶段数字化成本管控提供了可复制的技术范式。关键词:BIM+5D;改进挣值法;四量分析;动态成本控制;施工阶段Abstract:To address the prominent issues in construction phase cost control,such as lagging data collection,decoupling of schedule and cost information,and severe material waste,this study constructs a dynamic cost control system that integrates a BIM+5D linkage model,an improved Earned Value Method(EVM),and four?quantity analysis visualization. The system achieves dynamic monitoring and refined cost control through component?level real?time schedule?cost linkage,an hourly auto?calculated real?time cost deviation(RCD)warning mechanism,and dynamic comparison of budget quantity,purchase quantity,consumption quantity,and inventory quantity for main materials. The empirical application results indicate that this system offers a replicable technical approach for digital cost control during the construction phase.Keywords:BIM+5D;improved Earned Value Method;four quantity analysis;dynamic cost control;construction phase参考文献[1] 吴蓉蓉.基于BIM 5D的建筑工程施工成本控制研究[J].建筑经济,2017(6):32-35.[2] 刘平,许馨玉,房禹,等.基于BIM5D与改进挣值法的施工成本自动预警研究[J].土木建筑工程信息技术,2025(3):63-68.[3] Hou MengKe. The BIM-5D Technology Dynamically Manages the Data Monitoring in the Project[C]// Proceedings of Innovative Computing 2024. Springer,2024:129-139.[4] 中建七局第二建筑有限公司.阜阳碧桂园一期一标段工程项目BIM应用案例[Z].2020.[5] 黄莹,陈宗科,孟博.BIM5D在文旅项目施工成本管理中的应用[J].建筑经济,2025(12):44-50.[6] 李嘉欣.基于BIM技术的商业地产施工阶段成本控制研究[D].武汉:武汉工程大学,2018.[7] 杨海庆,王春晓.项目施工组织模式选择与成本控制的关联度分析[J].铁路工程技术与经济,2025(3):79-81,86.[8] 汪桂芳.EPC模式下项目建设成本控制研究[D].合肥:合肥工业大学,2020.[9] 中国建设工程造价管理协会.建设项目全过程造价咨询规程:CECA/GC 4-2017[S].北京:中国计划出版社,2018.建筑经济,2026(6):50-56