水电工程建筑材料价差调整研究
(1.中国电建集团西北勘测设计研究院有限公司,陕西 西安 710065;2.国能青海黄河玛尔挡水电开发有限公司,青海 果洛 814000)
- 文献要素
-
摘要:水电工程建设普遍具有复杂性及长期性,人工费、材料费、机具使用费价格水平的波动影响发承包双方利益,因此施工合同价款的调差成为建设各方关注的内容。本文以建筑材料价差调整为研究内容,在简要分析价格指数调差法和实际价格调差法的基础上,以某水电工程建筑材料价差调整为例,分别探讨两种方法对于案例工程的适用性,并详细分析适用方法下的边界条件、计算过程和计算结果;最后,对水电工程调差过程的常见问题进行提示,希望为其他类似项目建筑材料价差调整提供参考。关键词:材料价差调整;价格指数调差法;水电工程Abstract:The construction of hydropower projects is generally complex and long-term,and the fluctuations in the price levels of labor costs,material costs,and equipment usage fees affect the interests of both parties. Therefore,the adjustment of construction contract prices has become a concern for all construction parties. This article provides a brief analysis of the price index adjustment method and the actual price adjustment method. The price index adjustment method is used to calculate the price difference of hydropower projects,and a detailed analysis is conducted on the boundary conditions,calculation process,and calculation results. Finally,common problems in the adjustment process of hydropower projects are highlighted,hopes to provide reference for other similar projects.Keywords:material price difference adjustment;price index adjustment method;hydropower engineering参考文献[1] 陈欢,李海凌,王丹.基于价格指数调整价格差额法的价差调整应用分析[J].经营与管理,2019(2).[2] 周明科,杨海欧.实际价格调差法与价格指数调差法在工程造价中的比较应用[J].工程造价管理,2015(6).[3] 刘经纬,建碧碧,周延卫.浅议南水北调中线工程人工费和材料费价差调整[J].人民长江,2014(5).[4] 王双合.基于铁路项目材料价差调整问题研究[J].铁路工程技术与经济,2021(9).[5] 杨根初.工程材料调差常见问题及应对措施探析[J].工程造价管理,2021(6).建筑经济,2024(9):62-68