FIDIC合同调价公式在国际工程项目履约中的应用
(1.中铁国际集团有限公司,北京 100039;2.北京建工国际建设工程有限责任公司,北京 100055)
- 文献要素
-
摘要:材料价格波动是近年来国际工程承包市场普遍存在的问题。特别是项目履约周期较长的项目,其项目效益受市场价格因素影响的风险更大,国际工程承包商运用好合同条款中的调价公式是规避这一风险的有力工具。本文结合非洲某国项目的价格调整实践案例,解析在FIDIC 合同条款下,探讨如何在国际工程履约过程中应用调价公式来规避风险、控制成本和增加收益。关键词:FIDIC合同条款;调价公式;指数Abstract:The fluctuation of construction material prices has been a common problem in the international engineering contracting market in recent years. Especially for projects with long performance period,the risk of project benefits being affected by market price factors is greater. International engineering main contractors can effectively use the price adjustment formula in contract terms to avoid this risk. This article combines the price adjustment practice of a project in a certain African country to analyze how to use the price adjustment formula in the international engineering performance process to avoid risks,control costs,and increase profits under FIDIC contract terms.Keywords:FIDIC contract conditions;price adjustment formula;index参考文献[1] 穆飞,何瑞.国际工程承包合同中调价公式的应用[J].建筑经济,2009(S1):305-307.[2] 龚克.FIDIC合同中调价公式在国际承包工程中应用研究[D].重庆:重庆大学,2009.[3] 吴霄,汤孟刚.建筑材料价差调整办法的实际应用——以某水利项目为例[J].建筑经济,2022(12):69-76.[4] 李文涛.FIDIC施工合同条件下业主延期价调对项目成本/收益的影响研究——以巴基斯坦达苏水电站喀喇昆仑公路改线项目为例[J].工程建设与设计,2020(24):175-177.[5] 杜林鹏,徐冀飞,李尧.国际工程调价法及应用案例分析[J].国际经济合作,2011(5):47-51.[6] 中国工程咨询协会译.菲迪克(FIDIC)施工合同条件:1999年第1版[M].北京:机械工业出版社,2002.建筑经济,2024(6):73-78