污水处理厂项目投资估算编制要点与实践思考
(中国市政工程中南设计研究总院有限公司,湖北 武汉 430010)
- 文献要素
-
摘要:以广东省近三年12座新建污水处理厂建设项目的审定概算为研究样本,通过对工程费用、工程建设其他费用以及建设期贷款利息等造价指标进行细化整理,结合项目造价控制经验,进行污水处理厂建设项目估算要点分析,并提出工程费用准确估算、经验数据总结分析、多专业沟通配合是保证污水处理厂项目投资估算准确的基石,为后续污水处理厂项目投资估算的编制工作提供参考。关键词:污水处理厂;投资估算;编制要点;造价指标Abstract:Taking the approved budget of 12 newly-built sewage treatment plants in Guangdong Province in the past three years as research samples,this study analyzes the key and difficult points in the estimation of sewage treatment plant construction projects by refining and organizing the cost indicators of engineering costs,other construction costs,and interest on loans during the construction period. Combining with project cost control experience,this study also provides a summary and analysis of empirical data,accurate estimation of engineering costs,and multi-disciplinary communication and coordination are the cornerstones to ensure the accuracy of investment estimation for sewage treatment plant projects. This study aims to provide useful references and guidance for the preparation of investment estimation for subsequent sewage treatment plant projects.Keywords:sewage treatment plant projects;investment estimation;key points of compilation;cost index参考文献[1] 贺静.前期估算阶段造价控制——以某地下综合管廊工程为例[J].建筑经济,2021(5):55-57.[2] 高颖艳,张弢,艾菁菁,等.净水厂及污水处理厂投资估算阶段的风险控制[J].中国给水排水,2019(10):31-35.[3] 尚强强.给水工程设计概算编制中的问题与对策——以甘肃某城市饮用第二水源建设项目为例[J].建筑经济,2022(8):77-82.建筑经济,2024(6):56-61