浅谈北京轨道交通初步设计概算中价差预备费的计取
(北京市轨道交通建设管理有限公司,北京 100068)
- 文献要素
-
摘要:初步设计概算是建设项目总投资的依据,是建设项目实现各项管理目标的经济保证。本文分析北京轨道交通初步设计概算中价差预备费计取的现状及存在问题,依据现行的造价政策及市场实际情况,提出在初步设计概算批复中计列价差预备费项目,待工程结算审计后单独批复认可价差成本的解决方案,以期为概算编制及决策人员提供参考。关键词:初步设计概算;价差预备费;价差调整费用Abstract:The preliminary design budget estimate is the basis for the total investment of the construction project and the economic guarantee for the construction project to achieve various management objectives.This paper analyzes the current situation and problems of price difference reserve fee in the preliminary design budgetary estimate of Beijing rail transit. According to the current cost policy and the actual situation,this paper puts forward the solution of calculating the reserve fee for price difference in the approval of the preliminary design budget,and approving the cost of price difference separately after the audit of the project settlement,in order to provide reference for the budget preparation and decision-making personnel.Keywords:preliminary design budgetary estimate;price difference reserve fee;price difference adjustment cost参考文献[1] 忻剑鸣.从轨道交通工程设计概算角度谈投资控制[J].地下工程与隧道,2010(4):54-56+64.[2] 王立勇.浅析城市轨道交通工程造价指标[J].铁路工程造价管理,2014(3):18-22.[3] 吴朋.地铁工程设计阶段概算编制研究[J].铁路技术创新,2019(6):53-56.[4] 黄标良.轨道交通业主对设计及设计咨询考核管理的探讨[J].四川建材,2018(8):167-168.[5] 叶苗苗.轨道交通工程概算审核中的技术优化[J].上海建设科技,2019(1):76-77.[6] 蔡春.轨道交通工程造价的全过程控制探讨[J].科技创新导报,2017(2):122-123.[7] 李艳丽.城市轨道交通BT项目造价控制研究[D].重庆:重庆大学,2016.[8] 王颖.城轨交通工程投资估算编制要点及分析[J].铁路工程造价管理,2015(1):39-42.[9] 王文江.城市轨道交通工程设计咨询过程投资控制探讨[J].都市快轨交通,2005(6):9-11.[10] 文丹,许志宏,王凯南.价差预备费及有关税费在工程概算中的计列[J].人民长江,2008(21):89-90.[11] 张藤.建筑工程初步设计概算中存在的问题与应对策略探讨[J].工程技术研究,2023(8):122-124.[12] 冯建锋.关于工程造价中价差预备费的探讨[J].中州煤炭,2012(5):52-53+66.建筑经济,2023(11):75-79