高校基建工程竣工结算影响因素与应对措施研究
宁蕊蕊 王德臣
(大连工业大学基建处,辽宁 大连 116034)
文献要素

摘要:以某服装博物馆项目为例,通过对主体工程和装修工程相关资料分析,找出影响竣工结算的主要因素,包括人材机价格变化、工程量清单编制质量、设计变更、工程量签证等,提出明确合同条款、审计工程量清单、提高施工图设计质量、严格按图施工等应对措施,为今后高校基建工程的造价控制提供参考。
关键词:高校基建工程;竣工结算;影响因素;应对措施
Abstract:Taking the project of a costume museum as an example,this paper analyzes the completion settlement and finds the factors affecting the change of project cost,such as the change of manpower and machinery price,the quality of the bills of quantities,the change of design and the visa of quantity of works,etc,puts forward some measures,including clarifying the contract terms,examining and controlling the quality of the bills of quantities,controlling the design changes,and strictly following the drawing,in order to provide reference for the cost control of university capital construction projects in the future.
Keywords:university capital construction;completion settlement;influencing factors;countermeasures
参考文献
[1] 邵积荣,林丰强,陈思宁,等.工程项目竣工结算的内部控制研究[J].会计之友,2018(17):67-69.
[2] 赵维树,王珊珊.基于灰色关联分析的工程施工阶段的造价控制[J].洛阳理工学院学报(自然科学版),2019(6):25-29.
建筑经济,2021(03):29-31

下载地址

    你还没注册?或者没有登录?这篇论文要求至少是本站的注册会员才能阅读!

    如果你还没注册,请赶紧点此注册吧!

    如果你已经注册但还没登录,请赶紧点此登录吧!