海外道路工程项目索赔实例分析
(中交路桥建设有限公司海外分公司,北京 100027)
- 文献要素
-
摘要:以坦桑尼亚FD项目为例,分析工程量增加、施工用地交付延迟、箱涵图纸晚批等索赔起因,归纳索赔依据并计算索赔工期和款项。然后总结海外道路工程项目索赔的要点,供我国建筑业承包商参考。关键词:海外项目;道路工程;索赔;实例分析Abstract:Taking FD project in Tanzania as an example,this paper analyzes the causes of claim,including the increment of engineering quantities,late delivery of construction land,and delayed approval of box culvert working drawings,summarizes the claim basis,calculates time of extension and prolongation costs.Then,sums up the main points of the claim of overseas road project,which can provide reference for contractors of China.Keywords:overseas project;road engineering;claim;example analysis参考文献[1] 刘永锋.论海外工程的索赔策略[J].中国港湾建设,2016(10):73-76.[2] Society of Construction Law. SCL delay and disruption protocol[Z].2002.[3] Roger Knowles.200 contractual problems and their solutions(Third Edition)[M] . A John Wiley & Sons,Ltd,2012.[4] New south wales government. Handling prolongation and disruption claims[Z].2008.[5] 崔宏,张博.海外公路工程勘察设计项目工期索赔和费用索赔的分析计算方法[J].公路,2008(9):35-40.[6] 高建峰.海外EPC项目工程索赔的管理要点[J].科技与企业,2014(6):26+28.[7] 鱼峰,王力成.以某海外项目为例谈国际工程施工索赔[J].交通世界,2016(3):112-113.[8] 曹旭.巴基斯坦N水电站工程导流洞项目变更索赔典型案例分析[J].工程经济,2016(11):21-25.建筑经济,2018(10):64-66