堆型技术标准化对我国核电机组建造工期的影响研究
何昉 徐鬻 孔德泰 官思发
(中国核科技信息与经济研究院,北京 100048)
文献要素

摘要:基于我国核电机组建造历史数据,采用Cox比例风险模型,对堆型技术标准化影响核电机组建造工期的规模效应和学习效应进行实证检验。结果表明,特定堆型技术的历史机组建造数量每增加1台,在建机组完工的瞬时概率提高15.28%;而采取标准化堆型的业主管理的在建机组,任意时点的完工瞬时概率则提高174.7%;在新常态下,核电企业应更加注重堆型技术标准化,通过经验学习和批量化建造,不断提高核电经济竞争力。
关键词:堆型技术标准化;核电建造工期;生存分析;Cox比例风险模型
Abstract:Based on the data of construction of NPP in China,this paper studies the scale and learning effect of reactor technology standardization on construction duration of NPP through Cox proportional hazards model. The result shows that each additional unit of specific reactor technology is associated with a 15.28% increase in instantaneous probability of completion of unit,and under the more standardized reactor technology of owners,the instantaneous probability of completion of unit will increase 174.7%. Under the new normal,nuclear power enterprises should place more emphasis on reactor technology standardization and improve the economic competitiveness of nuclear power through mass construction and experiential learning.
Keywords:reactor technology standardization;construction duration of NPP;survival analysis;Cox proportional hazards model
参考文献
[1] World Nuclear Association. The world nuclear supply chain:Outlook 2035[R]. London:World Nuclear University Press,2016.
[2] 杨子春.影响实现核电建造总工期的主要风险浅析.中国核科学技术进展报告(第二卷)——中国核学会2011年学术年会论文集第3册[C].北京:中国原子能出版社,2012.
[3] 曾建新,王铁骊.基于技术轨道结构理论的核电堆型技术演变与我国的趋势[J].中国软科学,2012(3):31-40.
[4] 谭梦昭.我国核电的经济性:特点、发展现状及提高路径[J].经济视角,2014(7):82-84.
[5] 康俊杰,姚明涛,朱清源.核电建设周期、成本变化规律分
析[J].中国能源,2016(6):25-29.
[6] Csereklyei,Z.,Thurner,P.,Bauer,A.,Kuchenhoff,H. The effect of economic growth,oil price,and the benefits of reactor standardization:Duration of nuclear power plant construction revisited[J]. Energy Policy,2016(3):49-59.
[7] Boccard,N. The cost of nuclear electricity:France after Fukushima[J]. Energy Policy,2014(1):450-461.
[8] 张栋.世界核电发展及对我国的启示[J].能源技术经济,2010(12):5-10.
[9] Thurner,T.,Mittermeier,L.,Küchenhoff,H. How long does it take to build a nuclear power plant? A non-parametric event history approach with P-splines[J]. Energy Policy,2014(7):163-171.
[10] Joskow,P.,Parsons J. The Economic Future of Nuclear Power[J]. Daedalus,2009(4):45-59.
[11] 高志虎,程慧平.AP1000核电技术自主化和标准化运作模
式[J].中国核电,2014(2):156-159.
[12] 康椰熙,肖定生,司国建.核电建设的学习效应和标准化效
应[J].中国核电,2009(3):244-248.
[13] Jewell,J. Ready for nuclear energy? An assessment of capacities and motivations for launching new national nuclear power programs[J]. Energy Policy,2011(3):1041-1055.
[14] Therneau,P.,Grambsch,P. Modeling Survival Data:Extending the CoxModel[M]. New York:Springer,2000.
[15] Hamilton.应用STATA做统计分析[M].巫锡炜,焦开山,李丁等,译.北京:清华大学出版社,2017.
建筑经济,2018(06):48-52
 

下载地址

    你还没注册?或者没有登录?这篇论文要求至少是本站的注册会员才能阅读!

    如果你还没注册,请赶紧点此注册吧!

    如果你已经注册但还没登录,请赶紧点此登录吧!