装配式建筑进度计划缓冲及鲁棒性研究
陈伟 余杨清 周曼 邹松
(1.武汉理工大学,湖北 武汉 430070;2.武汉市建筑节能办公室,湖北 武汉 430072)
文献要素

摘要:装配式建筑工程具有在构件生产、物流运输、现场装配等多维作业空间并行实施的特征,其工程进度网络计划复杂。为保证多维作业空间的工作协调有序进行,分别构建基于关键链技术的装配式建筑工程集中缓冲、分散缓冲进度计划;建立质量鲁棒性、解鲁棒性两类指标对计划的稳定性进行评价,并进行实证分析。结果表明:集中缓冲进度计划在质量鲁棒性方面优于分散缓冲进度计划;考虑工序开始时间稳定性的分散缓冲进度计划更有利于控制项目进度。
关键词:装配式建筑;关键链技术;集中缓冲;分散缓冲;鲁棒性
Abstract:The prefabricated building project has the characteristics of the parallel implementation of the multi-dimensional work space,such as component production,logistics transportation and field assembly,the engineering schedule network plan of prefabricated building is complex. In order to ensure that the work of multidimensional operating space carries out coordinately and orderly,this paper respectively builds the concentrated buffers and scattered buffers schedules for prefabricated building projects based on the critical chain. Then,establishes two kinds of index including quality robustness and solution robustness to evaluate the stability of the schedules,and conducts an empirical analysis. The results show that the concentrated buffers schedule is better than scattered buffers schedule in terms of quality robustness. The scattered buffers schedule which consider the start time stability of the process has more benefical to the project schedule management control.
Keywords:prefabricated building;critical chain technology;concentrated buffer;scattered buffer;robustness
参考文献
[1] Goldratt EM. Critical chain[M]. Great Barrington:North River Press,1997.
[2] 马国丰,尤建新.关键链项目群进度管理的定量分析[J].系统工程理论与实践,2007(9):54-60.
[3] 林晶晶,周国华,杨琴.考虑资源可替代性的关键链调度方法研究[J].管理学报,2010(8):1233-1236.
[4] 李俊亭,杨睿娟.关键链多项目进度计划优化[J].计算机集成制造系统,2013(3):631-640.
[5] 彭武良,王成恩.关键链项目调度模型及遗传算法求解[J].系统工程学报,2010(2):123-131.
[6] Hoel K,Taylor S G. Quantifying buffers for project schedules[J].Production and Inventory Management Journal,1999(2):43-47.
[7] 施蹇,王雅婷,龚婷.项目缓冲设置方法及其评价指标改
进[J].系统工程理论与实践,2012(8):1739-1746.
[8] 李明,徐哲,于静.基于帕金森定律的关键链缓冲设置方
法[J].计算机集成制造系统,2013(12):3177-3183.
[9] Harold Kerzner. Project management:A systems approach to planning,scheduling and controlling(9e)[M]. Hoboken:John Wiley & Sons,2009.
[10] Leach L.P. Critical chain project management(2nd Edition)[M]. Norwood MA:Artech House,INC,2005.
[11] 别黎,崔南方.关键链动态缓冲监控方法研究[J].中国管理科学,2010(6):97-103.
[12] Al Fawzan M,Haouari M. A bi-objective model for robust resource-constrained project scheduling[J]. International Journal of Production Economics,2004(4):175-187.
[13] 何正文,刘人境,徐渝.基于随机活动工期的资源约束项目鲁棒性调度计划[J].系统工程理论与实践,2013(3):650-659.
[14] Leus,R. The generation of stable project plans[M]. Brussels:Katholieke Universiteit Leuven,2003.
[15] Van De Vonder S,Demeulemeester E,etal. The trade-off between stability and makespan in resource constrained project scheduling[J]. International Journal of Production Research,2006(2),215-236.
[16] 寿涌毅,王伟.基于鲁棒优化模型的项目调度策略遗传算
法[J].管理工程学报,2009(4):148-152.
[17] 张静文,刘耕涛.基于鲁棒性目标的关键链项目调度优化[J].系统工程学报,2015(1):135-144.
[18] 刘琼,林魁,张超勇,等.基于关键链多项目鲁棒调度[J].计算机集成制造系统,2012(4):813-820.
[19] 张立辉,潘楚云,邹鑫.重复性项目调度与网络模型转化方法研究[J].管理科学学报,2014(6):49-59.
[20] 田文迪,崔南方,付樟华.基于分支定界法的关键链项目计划重排[J].计算机应用研究,2011(11):4035-4039.
建筑经济,2018(02):33-39