不可抗力(台风)条件下建设工程项目措施费索赔研究
(078工程指挥部,海南 文昌 571300)
- 文献要素
-
摘要:解读我国《合同法》、《民法通则》等相关的不可抗力法律条文和《建设工程施工合同(示范文本)》(GF-2013-0201)与FIDIC合同条件中关于不可抗力合同条款;结合工程实际和相关惯例做法,分析不可抗力(台风)发生后措施项目费索赔争议问题,并得出几点启示。关键词:建设工程;不可抗力;合同条款;措施费Abstract:The paper analyzes China’s relevant legal provisions of fore majeure for “Contract Law”,“General Principles of Civil Law”,and the contract clause of force majeure in “Construction Contract(Model Text)(GF-2013-0201)and FIDIC contract conditions. Combined with the project practice and related practices,discuss the disputes of the claim for project measures fee after the force majeure(typhoon),and puts forward some suggestions.Keywords:construction project;force majeure;contract clause;measure fee参考文献[1] 住建部.建筑安装工程费用项目组成(建标〔2013〕44号)[S].2013.[2] 建设部.建设工程工程量清单计价规范GB50500-2003[S].北京:中国计划出版社,2003.[3] 王洪强,吕慧敏,马亮,等.异常恶劣气侯条件下承包商停工费用索赔研究[J].建筑经济,2016(3):29-31.[4] FIDIC. Conditions of contract for construction,for building and engineering works designed by the employer[M]. First Edition,Switzerland:FIDIC,1999.[5] 柯洪.建设工程计价[M].北京:中国计划出版社,2013.工程经济,2017(03):15-18