工程赶工费用索赔处理的实践与探讨
(北京中天恒达工程咨询有限责任公司,北京 100081)
- 文献要素
-
摘要:阐述工程赶工索赔及处理原则,研究处理赶工降效费用的实物量总费用法和单价补差法,介绍水电工程赶工费处理案例,并从发包人视角提出工程赶工费用索赔预防和规避策略及建议。关键词:赶工费用;索赔;降效;合同管理Abstract:Analyzes the calculation principle and pattern of cost of crashed task,studies the total cost method of physical quantity and compension method of unit price that dealing with cost of crashed task due to efficiency decrease,introduces the practice case that dealing with claiming for cost of construction accelerative of water-power engineering,puts forward the comprehensive processing strategy and suggestion that can prevent and avoid the claiming for cost of crashed task from the view of developer.Keywords:cost of crashed task;claim;efficiency decrease;contract management参考文献[1] 住房和城乡建设部.GB/50500-2013建设工程工程量清单计价规范[S].北京:中国计划出版社,2013.[2] 王嘉明.水电工程赶工费用计算的几种方法探讨[J].四川水利,2009(2):253.[3] 朱建国,王婷婷,徐伟.共同延误下加快施工费用索赔计算原则研究[J].建筑经济,2016(3).[4] 付彬,邰先高.水电工程赶工费用计算方法和补偿方式[J].云南水力发电,2014(2):148.[5] 曹旭.巴基斯坦N水电站工程导流洞项目变更索赔典型案例分析[J].工程经济,2016(11).建筑经济,2017(2):40-43